When investing in factory setups in Vietnam, environmental compliance is a critical aspect that cannot be overlooked. This guide aims to provide investors with practical strategies for environmental compliance, helping you smoothly conduct business in Vietnam while avoiding losses and complications due to environmental issues.

1. Preliminary Planning Stage

1.1 Environmental Impact Assessment (EIA)

Action Steps:

  1. Hire a qualified Vietnamese EIA agency to prepare the necessary documents: project overview, production process, expected emission data, etc.
  2. Prepare the EIA report (usually takes 2-3 months).
  3. Submit the report to the provincial Department of Natural Resources and Environment.
  4. Attend review meetings and answer questions from experts.
  5. Revise the report based on feedback to obtain approval.

Key Timelines:

  • The EIA approval must be completed before the project starts.
  • It typically takes 30-45 working days from submission to approval.

Practical Advice:

  • Choose an EIA agency with experience in Chinese projects for better communication.
  • Fully disclose project information to avoid penalties for inaccurate information later.
  • Keep all communication records and documents for future inspections.

1.2 Site Selection and Planning

Action Steps:

  1. Research the distribution of industrial zones in Vietnam (reference: Vietnam Industrial Zones Authority website www.khucongnghiep.com.vn).
  2. Evaluate the environmental infrastructure of target industrial zones.
  3. Understand local environmental requirements and enforcement strength.
  4. Include environmental costs in the overall investment budget.

Practical Advice:

  • Prioritize industrial zones with well-developed environmental infrastructure to reduce investment in environmental facilities.
  • Consult with other Chinese enterprises already investing locally to understand actual environmental enforcement practices.

2. Construction Phase

2.1 Construction of Environmental Facilities

Action Steps:

  1. Design an environmental facilities plan according to EIA requirements.
  2. Select qualified environmental equipment suppliers (consult the list recommended by the Vietnam Environmental Administration).
  3. Invite environmental experts for regular inspections during construction.
  4. Complete commissioning and trial operation of environmental facilities.

Key Timelines:

  • Environmental facilities must be designed, constructed, and put into use simultaneously with the main project.

Practical Advice:

  • Consider future expansion needs and appropriately increase the processing capacity of environmental facilities.
  • Retain all design drawings, purchase contracts, and commissioning reports of environmental facilities.

2.2 License Processing

Required Licenses:

  • Emission Permit
  • Hazardous Waste Management Registration Certificate (if applicable)
  • Radiation Safety License (if applicable)

Action Steps:

  1. Gather necessary application materials (including EIA approval, environmental facility acceptance report, etc.).
  2. Submit applications to the provincial environmental management department.
  3. Accept on-site inspections.
  4. Obtain relevant licenses.

Key Timelines:

  • Emission Permit: to be completed within 20 working days from the date of application.
  • Licenses are typically valid for five years; note the renewal period.

3. Operation Phase

3.1 Daily Monitoring and Record-Keeping

Monitoring Items:

  • Wastewater: pH, COD, BOD5, Total Nitrogen, Total Phosphorus, etc.
  • Exhaust Gas: Particulate Matter, SO2, NOx, VOCs, etc.
  • Noise: Boundary Noise

Action Steps:

  1. Develop an annual monitoring plan.
  2. Hire qualified monitoring agencies for regular testing.
  3. Install online monitoring equipment (applicable to key pollutant discharge units).
  4. Establish an environmental monitoring log to record daily operating data.

Practical Advice:

  • Use digital tools to manage monitoring data for easy analysis and reporting.
  • Regularly compare self-test data with third-party test results to ensure accuracy.

3.2 Management of Pollutants and Compliance with Discharge Standards

Action Steps:

  1. Familiarize yourself with relevant discharge standards (e.g., QCVN 40:2011/BTNMT for wastewater).
  2. Establish internal warning values lower than regulatory limits.
  3. Regularly maintain environmental facilities to ensure proper operation.
  4. Develop an emergency response plan to handle exceedances.

Practical Advice:

  • Appoint an environmental officer responsible for daily supervision and coordination.
  • Establish a reward and penalty mechanism to enhance environmental awareness among all employees.

3.3 Management of Solid and Hazardous Waste

Action Steps:

  1. Classify, collect, and store solid waste.
  2. Establish a hazardous waste management log.
  3. Sign agreements with qualified waste disposal units.
  4. Standardize the use of hazardous waste transfer manifests.

Practical Advice:

  • Regularly check the qualifications of waste disposal units to avoid being implicated by third-party violations.
  • Consider waste reduction and resource recovery options to reduce disposal costs.

3.4 Emergency Management

Action Steps:

  1. Develop an environmental emergency response plan.
  2. Equip necessary emergency equipment and supplies.
  3. Conduct regular emergency drills (at least once a year).
  4. Update and revise the plan promptly.

Practical Advice:

  • Establish good relations with local environmental departments and maintain open communication channels.
  • Prepare emergency plans in both Chinese and Vietnamese to ensure all employees understand.

4. Continuous Improvement

4.1 Compliance Assessment

Action Steps:

  1. Conduct an internal environmental compliance assessment every six months.
  2. Hire a third-party agency for an annual compliance audit.
  3. Monitor the latest changes in environmental regulations (keep an eye on announcements on the Vietnam Environmental Administration website).
  4. Develop and implement a remediation plan.

4.2 Cleaner Production Audits

Action Steps:

  1. Form a cleaner production audit team.
  2. Identify key energy and water consumption areas.
  3. Propose and implement cleaner production solutions.
  4. Evaluate the effectiveness of implemented solutions.

Practical Advice:

  • Actively participate in industry association activities to learn advanced environmental practices.
  • Consider applying for ISO 14001 environmental management system certification.

5. Case Study

Case: A Chinese Textile Company’s Path to Environmental Compliance in Vietnam

Background: Company A invested in a factory in Dong Nai Province, Vietnam, producing denim garments.

Challenges:

  1. Wastewater treatment not up to standard, resulting in warnings from local environmental departments.
  2. Workshop noise disturbed residents, leading to complaints from nearby communities.

Solutions:

  1. Wastewater Treatment:Hired professional consultants to diagnose the wastewater treatment system; Added treatment units to increase processing capacity.
  2. Noise Control:Installed soundproof covers for high-noise equipment; Optimized plant layout, relocating high-noise workshops away from residential areas.

Results:

  • Wastewater was discharged steadily within standards, receiving commendation from environmental departments.
  • Noise issues were resolved, significantly improving community relations.
  • Enhanced corporate brand image, leading to more international orders.

Experience Summary:

  1. Prevention is key; promptly address problems when discovered.
  2. Actively communicate with the government and community to build trust.
  3. Environmental investment is essential and can yield good returns in the long run.

6. Useful Resources

  1. Vietnam Environmental Administration: www.vea.gov.vn
  2. Ministry of Planning and Investment of Vietnam: www.mpi.gov.vn
  3. Economic and Commercial Office of the Chinese Embassy in Vietnam: vn.mofcom.gov.cn

Environmental compliance is the foundation for factory operations in Vietnam and a reflection of corporate social responsibility and sustainable development. Through systematic planning, strict implementation, and continuous improvement, investors can establish themselves in the Vietnamese market and achieve good growth. Remember, environmental investment is not only for compliance but also a guarantee of long-term competitiveness.

Publications

Latest News

Our Consultants

Want the Latest Sent to Your Inbox?

Subscribing grants you this, plus free access to our articles and magazines.

Our Vietnam Company:
Enterprise Service Supervision Hotline:
WhatsApp
ZALO

Copyright: © 2024 Vietnam Counseling. All Rights Reserved.

Login Or Register